Urban rehabilitation project
NYDOP-3.1.1/B-2009-0005
Start date of the project: 02.10.2009
Closing date of the project: 30.04.2015
- Internal road Phase I. (it relieves the city center from heavy traffic)
- Renovation of Kossuth Lajos street
- Market square surface works
- Parking area in Budai Nagy Antal Street
- Construction of underground car park at Sütő Street
- Construction of Customer Service Office
- Reconstruction of „Csipkeházak”
- Reconstruction of the area in front of the Mayor’s Office and Dísz square
NYDOP-3.1.1/B2-13-2k-2013-0001
Start date of the project: 11.06.2013
Closing date of the project: 31.12.2014
The aim of the project is to make the living environment more livable as a result of the renewal of the physical environment. Within this framework, the implementation covered the following elements: renovation of rental housing, development of the green areas, renovation of public institutions.
In order to achieve the goals of the project, the municipality has implemented the following improvements:
- Block interior rehabilitation
- Reconstruction of a retired home
- The Social Club has been renewed
- Implementation of a number of additional “soft” activities (community, training, public safety programs)
NYDOP-3.1.1/B1-13-k-2013-0005
Start date of the project: 30.09.2013
Closing date of the project: 31.12.2015
- The Dísz square was renovated during this period
- Northern Road II. phasis (it relieves the city center from heavy traffic)
- Renovation of the market hall
- October 6 Square – Batthyány street – Budai Nagy Antal street: construction of a junction with traffic lights
- Reconstruction of the northern section of Kölcsey Ferenc Street, with the creation of sidewalk connections and landscaping
- The new road connections of the LÉSZ Kft. were established
- „Flower yard” development
Within the framework of the portal program carried out a complex facade reconstruction on the downtown properties at Kazinczy square, Széchenyi square, Kossuth street and Eötvös alley.